An output of the Plan Quality Management process is:

Posted by: Pdfprep Category: CAPM Tags: , ,

An output of the Plan Quality Management process is:
A . A process improvement plan.
B . Quality control measurements.
C . Work performance information.
D . The project management plan.

Answer: A

Explanation:

Process: 8.1 Plan Quality Management

Definition: The process of identifying quality

requirements and/or standards for the project and its deliverables and

documenting how the project will demonstrate compliance with quality

requirements and/or standards.

Key Benefit: The key benefit of this process is that it provides guidance and direction on how quality will be managed and validated throughout the project.