An output of the Perform Integrated Change Control process is:
A . Deliverables.
B . Validated changes.
C . The change log.
D . The requirements traceability matrix.
Answer: C
Explanation:
An output of the Perform Integrated Change Control process is:
A . Deliverables.
B . Validated changes.
C . The change log.
D . The requirements traceability matrix.
Answer: C