Posted by: Pdfprep Category: CAPM Tags: CAPM exam questions, CAPM practice exam, CAPM Certification Post Date: November 30, 2020 Pdfprep2020-11-30T13:21:09+00:00 An output of the Perform Integrated Change Control process is:A . Deliverables.B . Validated changes.C . The change log.D . The requirements traceability matrix. View Answer Answer: C Explanation: Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.