Posted by: Pdfprep
Post Date: December 24, 2020
An output of the Develop Project Team process is:
A . Organizational process assets.
B . Enterprise environmental factors updates.
C . Project staff assignments.
D . Organizational charts and position descriptions.
Answer: B
Leave a Reply