An IT manager is working with a project manager from another subsidiary of the same multinational organization. The project manager is responsible for a new software development effort that is being outsourced overseas, while customer acceptance testing will be performed in house. Which of the following capabilities is MOST likely to cause issues with network availability?
A . Source code vulnerability scanning
B . Time-based access control lists
C . ISP to ISP network jitter
D . File-size validation
E . End to end network encryption
Answer: B