An IS auditor is conducting a pre-implementation review to determine a new system’s production readiness. The auditor’s PRIMARY concern should be whether:
A . the project adhered to the budget and target date
B . users were involved in the quality assurance (QA) testing
C . there are unresolved high-risk items
D . benefits realization has been evidenced
Answer: C