An input to the Manage Project Team process is:
A . Work performance reports.
B . Change requests.
C . Activity resource requirements.
D . Enterprise environmental factors.
Answer: A
Explanation:
Process: 9.4 Manage Project Team
Definition: The process of tracking team member performance,
providing feedback, resolving issues, and managing changes to optimize project
performance.
Key Benefit: The key benefit of this process is that it influences team behavior, manages conflict, resolves issues, and appraises team member performance.
Inputs