PdfPrep.com

An input to the Manage Project Team process is:

An input to the Manage Project Team process is:
A .  Work performance reports.
B .  Change requests.
C .  Activity resource requirements.
D .  Enterprise environmental factors.

Answer: A

Exit mobile version