An input to Develop Project Charter is a/an:
A . Business case.
B . Activity list.
C . Project management plan.
D . Cost forecast.

Answer: A

Explanation:

Process: 4.1. Develop Project Charter

Definition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.