All of the following statements about Risk Communications are true, EXCEPT:
A . The Stakeholders should be continuously informed about risks, including the potential impact of these risks and the plans for responding to each risk.
B . The Scrum Team may also discuss specific risks related to their Tasks with the Product Owner during Daily Standup Meetings.
C . The Product Owner is responsible for the prioritization of risks and for communicating the prioritized list to the Scrum Team.
D . Information related to risks is maintained and updated through the Risk Burndown Chart.
Answer: B
Explanation:
Because stakeholders have an interest in the project, it is important to communicate with them regarding risks. Information provided to stakeholders related to risk should include potential impact and the plans for
responding to each risk. This communication is on-going and should occur in parallel with the four sequential steps discussed thus far―risk identification, assessment, prioritization and mitigation. The Scrum Team may also discuss specific risks related to their Tasks with the Scrum Master during Daily Standup Meetings. The Product Owner is responsible for the prioritization of risks and for communicating the prioritized list to the Scrum Team. An important tool which can be used for communicating information related to risks is the Risk Burndown Chart.
Reference: http://blog.scrumstudy.com/risk-management-in-scrum/