All of the following are possible explanations for a significant unfavorable material efficiency variance except:
A . Cutbacks in preventive maintenance.
B . An inadequately trained and supervised labor force.
C . A large number of rush orders.
D . Production of more units than planned for in the master budget.
Answer: D