After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD.

After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD.

This is an example of____________.
A . Qualitative risk analysis
B . Risk Appetite
C . Quantitative risk analysis
D . Risk Tolerance

Answer: C