According to the Change theme, which of the following contains the steps of the recommended issue and change control procedure?

According to the Change theme, which of the following contains the steps of the recommended issue and change control procedure?
A . Capture, Examine, Analyze Impact, Review Probability, Implement Action
B . Capture, Log, Review, Resolve
C . Assess, Decide, Escalate, Implement
D . Capture, Examine, Propose, Decide, Implement

Answer: D