According to the Change theme, which of the following contains the steps of the recommended issue and change control procedure?
A . Capture, Examine, Analyze Impact, Review Probability, Implement Action
B . Capture, Log, Review, Resolve
C . Assess, Decide, Escalate, Implement
D . Capture, Examine, Propose, Decide, Implement
Answer: D