Posted by: Pdfprep
Post Date: December 6, 2020
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
A . Plan Stakeholder Management
B . Identify Stakeholders
C . Manage Stakeholder Engagement
D . Control Stakeholder Engagement
Answer: A
Explanation:
Leave a Reply