A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
A .  Plan Stakeholder Management
B .  Identify Stakeholders
C .  Manage Stakeholder Engagement
D .  Control Stakeholder Engagement

Answer: A