A security administrator was recently hired in a start-up company to represent the interest of security and to assist the network team in improving security in the company. The programmers are not on good terms with the security team and do not want to be distracted with security issues while they are working on a major project. Which of the following is the BEST time to make them address security issues in the project?
A . In the middle of the project
B . At the end of the project
C . At the inception of the project
D . At the time they request
Answer: C