A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable.
This could have been avoided if the project team had implemented:
A . Quality assurance.
B . Astakeholder management plan.
C . Project team building.
D . Integrated change control.
Answer: D