A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner.

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner.

This issue could have been avoided if they had created and followed a:
A .  risk management plan
B .  human resource management plan
C .  scope management plan
D .  procurement management plan

Answer: D