A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
A .  Historical information and the lessons-learned database.
B .  Historical information and the stakeholder register.
C .  Organizational process assets and the lessons-learned database.
D .  Project documents and historical information.

Answer: A