A project manager requesting industry groups and consultants to recommend project intervention is relying on:
A . Communication models.
B . Stakeholder participation.
C . Expert judgment
D . Enterprise environmental factors.
Answer: C
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
A . Communication models.
B . Stakeholder participation.
C . Expert judgment
D . Enterprise environmental factors.