A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time . The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?

A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time . The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?
A . .93
B . .82
C . $323,889
D . -$38,889

Answer: A