A master PM can be used to do which of the following?

Posted by: Pdfprep Category: C2010-555 Tags: , ,

A master PM can be used to do which of the following?
A . Create a job plan revision.
B . Generate work orders for associated PMs.
C . Create associated PMs for an item’s location.
D . Change the status of work orders generated from associated PMs.

Answer: C

Explanation:

Reference: http://www.redbooks.ibm.com/redbooks/pdfs/sg247761.pdf (page 55)