A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Posted by: Pdfprep Category: CAPM Tags: , ,

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
A . Start-to-start (SS).
B . Start-to-finish (SF).
C . Finish-to-start (FS).
D . Finish-to-finish (FF).

Answer: C

Explanation:

– A finish-to-start (FS) relationship between two activities implies that the initiation of successor is dependent on the completion of predecessor.

– A finish-to-finish (FF) relationship between two activities implies that the completion of successor is dependent on the completion of predecessor.

– A start-to-start (SS) relationship implies that the initiation of successor is dependent on the initiation of predecessor.

– A start-to-finish (SF) relationship between two activities implies that the completion of successor is dependent on the initiation of its predecessor