A company is starting to introduce Agile practices, and the project manager has been asked to identify how to introduce the new process. The project manager’s initial plan should be to:
A . Institute daily standup meetings immediately.
B . Communicate the Agile Manifesto to the team.
C . Balance teaching principles with Agile practices.
D . Rate the team’s progress in learning new methods.
Answer: C