A Belt gathered the following defect data for a shoe production line and wanted to assemble it into a Pareto Chart.
The correct order from left to right in the chart would be:
Data:
Frame 32
Handle 41
String 17
Grip 23
A . String, Grip, Frame, Handle
B . Frame, String, Grip, Handle
C . Handle, Frame, Grip, String
D . String, Frame, Grip, Handle
Answer: C