The following is a list of statements about stakeholders and stakeholder management.
a) A customer can be considered as a stakeholder in a project.
b) A supplier can be considered as a stakeholder in a project.
c) Stakeholders’ positions do not remain static during the life of the project.
d) Communication must not be tailored to each stakeholder in the project.
Which of the following is correct?
A . Statements a, b and c are correct, statement d is incorrect.
B . All four statements are correct.
C . Statements a and c are correct, statements b and d are incorrect.
D . Statements b and c are correct, statements a and d are incorrect.
Answer: A