Which of the following specifically can MRP I and MRP II NOT assist with?


Material requirements planning (MRP I) and manufacturing resource planning (MRP II) are computerised systems used for planning the requirements for raw materials, work-in-progress and finished items and integrating with other production processes. These systems enable strong relationships to be forged with suppliers as orders can be placed with suppliers in good time to fulfill customer requirements and expectations, as well as other processes related to materials planning.

Which of the following specifically can MRP I and MRP II NOT assist with?
A . Financial requirements planning
B . Equipment utilisation planning
C . Decision support planning
D . Labour schedule planning

Answer: C

Leave a Reply

Your email address will not be published.