Posted by: Pdfprep
Post Date: January 24, 2021
A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these two lists.
What do you have to consider for the two lists at this stage? (Choose two)
A . The stock/requirements list was updated the moment it was accessed.
B . The MRP list displays the production order.
C . The MRP list has the status "processed".
D . The stock/requirements list displays the production order.
Answer: A,D
Leave a Reply