Posted by: Pdfprep
Post Date: February 7, 2021
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
– Start: 7:00:00 a.m.
– End: 3:00:00 p.m.
– Break duration: 1 hour
– Rate of utilization: 80%
– Overload: 110%
– Number of individual capacities: 1
How large is the standard available capacity?
A . 8 hours
B . 5.6 hours
C . 6.16 hours
D . 7 hours
Answer: B
Leave a Reply