What are the responsibilities of the Project Team on level 4 in the picture below? There are 2 correct answers to this question.
A . Set Project policy, standards and oversight
B . Set business priorities, goals and objectives
C . Identify and resolve issues and risks
D . Perform status reporting and communication
Answer: C,D