Which should be done during the process Closing a Programme?
A . Confirm that key stakeholders are satisfied with the improvements
B . Provide an opportunity to plan a post-project review
C . Identify the need for future assessment of benefit realization
D . Enable all outstanding risks to be closed
Answer: C