A development team is utilizing a project area built on the scrum template. The scrum master wants to understand how much estimated work remains in the iteration and projection for completion.
What action would the scrum master take to assess this?
A . Examine the Ranked List of work items.
B . View the Burndown Chart in the plan Details.
C . Compare the plan’s Initial to Planned snapshot.
D . Review the Effective Estimate and Time Spent in the Roadmap.
Answer: D