Which switch configuration can meet these requirements?

Posted by: Pdfprep Category: HPE0-V14 Tags: , ,

A customer is planning to deploy a branch office server rack.

The environment will have the following requirements:

– Single rack with 20 HPE ProLiant DL360 Gen10 Servers.

– Each Server will have 6 x 10G SFP+ Ports.

– Each Server will have a dedicated iLO port.

– The customer requires that only two switches be used.

– The customer requires separate control planes.

Which switch configuration can meet these requirements?
A . 2 × HPE 5945 Series switch with IRF
B . 2 × Aruba 8325 Series switches with VSX
C . 2 × HPE 5945 Series switches standalone
D . 2 × Aruba 8325 Series switches with backplane stacking.

Answer: C