The Product Owner informs the team that the release will be date-driven.
What kind of buffer for uncertainty is most important to use in this type of release?
A . Budget buffer
B . Feature buffer
C . Padding buffer
D . Schedule buffer
Answer: D
Explanation:
In projects where time is of the essence, a schedule buffer can be implemented.
Reference: https://www.productbookshelf.com/2012/09/agile-estimating-and-planning/