A Scrum Team is supposed to deliver potentially snippable software at the end of each Sprint. During the last Sprint the Team did not deliver a potentially shippable increment. The correct question to ask is: “What can we do to make sure we do better in the next Sprint?”
Who is responsible for making sure this question asked?
A . The Development Team
B . The Product Owner
C . The Project Manager
D . The Scrum Master
Answer: D