Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?
A . This conflicts with the principle of Self-Management of the Development Team.
B . The Product Owner does not know the velocity of the Development Team.
C . The Scrum Master is responsible for the velocity of the Development Team.
D . The Scrum Master and the Product Owner must agree on the workload of the Development Team.
Answer: A