A software development manager is taking over an existing software development project. The team currently suffers from poor communication due to a long delay between requirements documentation and feature delivery. This gap is resulting in an above average number of security-related bugs making it into production. Which of the following development methodologies is the team MOST likely using now?
A . Agile
B . Waterfall
C . Scrum
D . Spiral
Answer: B