You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite for the Sprint Review to demo the items completed in the Sprint. Who should you invite as a required attendee to the Sprint Review?
Product Owner(s)
Development Team
Business Users
A . 1, 2, and 3
B . 1 and 2 only
C . The entire company
D . 1 only
Answer: B