You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information: Sprint 1: 10 pontos Sprint 2: 11 pontos Sprint 3: 15 pontos Sprint 4: 14 pontos Sprint 5: 15 pontos
Sprint 6: 10 pontos The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
A . 6
B . 5
C . 4
D . 3
Answer: B