Posted by: Pdfprep
Post Date: November 3, 2020
During the daily standup meeting, a team member states that an issue has been encountered. This leads to the team members getting into a problem-solving discussion.
How should the ScrumMaster respond?
A . Ask the team members to table the discussion until after the meeting is over.
B . If the item is really important, allow the discussion to expedite resolution of the issue.
C . Abruptly end the daily standup meeting and schedule another meeting to discuss the issue.
D . Ask the team how they would like to use the daily standup meeting for that day.
Answer: A
Leave a Reply