Posted by: Pdfprep Category: PMI-200 Tags: PMI-200 exam questions, PMI-200 practice exam, PMI-ACP Certification Post Date: November 20, 2020 Pdfprep2020-11-20T05:15:03+00:00 The cost estimation techniques used on Agile projects are:A . Rule of thumbB . Bottom-upC . ParametricD . Top-down View Answer Answer: D Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.