Posted by: Pdfprep
Post Date: October 22, 2020
Which of the following is TRUE about most project life cycles?
A . Staffing level is highest at the start.
B . The stakeholders’ influence is highest at the start.
C . The level of uncertainty is lowest at the start.
D . The cost of changes is highest at the start.
Answer: B
Leave a Reply