Posted by: Pdfprep
Post Date: November 4, 2020
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
A . project documents updates.
B . project management plan updates.
C . change requests.
D . work performance information.
Answer: D
Leave a Reply