Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 12, 2020 Pdfprep2020-11-12T14:20:55+00:00 The following is a network diagram for a project. The free float for Activity H is how many days?A . 4B . 5C . 10D . 11 View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.