Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 1, 2020 Pdfprep2020-11-01T13:14:32+00:00 Which element does a project charter contain?A . Management reservesB . Work breakdown structureC . Stakeholder listD . Stakeholder register View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.