Posted by: Pdfprep
Post Date: November 9, 2020
Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?
A . Control Quality
B . Monitor and Control Project Work
C . Control Scope
D . Perform Integrated Change Control
Answer: D
Leave a Reply