Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: December 4, 2020 Pdfprep2020-12-04T18:15:05+00:00 The number of potential communication channels for a project with 5 stakeholders is:A . 10.B . 12.C . 20.D . 24. View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.