The process of identifying and documenting relationships among the project activities is known as:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The process of identifying and documenting relationships among the project activities is known as:
A .  Control Schedule.
B .  Sequence Activities.
C .  Define Activities.
D .  Develop Schedule.

Answer: B