Posted by: Pdfprep
Post Date: December 3, 2020
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
A . Stakeholder register
B . Scope management plan
C . Stakeholder management plan
D . Project charter
Answer: A
Leave a Reply